Hand-mounted climate wall on the embankment on Weddinger Straße / Weißer Weg
For the project in Goslar-Immenrode, a new climate wall was erected on an embankment. The construction site was located in the Weddinger Straße / Weißer Weg area and was implemented in the period from 08.12. to 11.12.2025.
The climate wall has a length of 105.00 m and a height of 1.00 m. By positioning it on the embankment, a functional and visually clean solution was created that adapts to the existing terrain and clearly structures the area.
A particular challenge in this project was the fact that it was carried out without construction machinery. As the use of machinery on the construction site was not permitted, the entire installation was carried out by hand. This made careful planning and precise execution on site particularly important.
Despite the limited framework conditions, the climate walls were realized within a few days. The project shows that climate walls can be implemented flexibly even under challenging construction site conditions – cleanly, efficiently and adapted to the respective situation on site.
- Construction period: 08.12. to 11.12.2025
- Climate wall: 105.00 m length
- Height: 1.00 m
- Construction site: Weddinger Straße / Weißer Weg, Goslar-Immenrode
- Special feature: Climate wall on wall
- Execution: Installation by hand, as the use of construction machinery was not approved